| The beneficiary shall: | Hospital with a clinic Prievidza based in Bojnice, Hospital 2, 972 01 Bojnice |
| Project name: | Construction of new emergency intake and central sterilization and reduction of energy consumption Monoblock A combined with reconstruction of selected departments |
![]()
| Activity name | Expected date of completion |
Real date of completion |
|
| Part 1 Construction of new emergency reception and central sterilisation | 4/2026 | ||
| phase 1 | 11/2020 | ||
| Construction of new emergency reception and central sterilisation - the second phase (building part) |
4/2026 | ||
| Procurement on construction contractor | 12/2024 | ||
| Construction of central sterilisation | 1/2026 | ||
| Installation of renewables for urgent reception and central sterilisation | 4/2026 | ||
| phase 2 (health technologies) | 10/2025 | ||
| Part 2 Reducing the energy intensity of Monobloc AE and reconstruction of selected departments |
5/2026 | ||
| Building a department of OAIM in area 1. PP monoblock, block AE (building part) | 2/2024 | 2/2024 | |
| Building a department of OAIM in area 1. PP monoblock, AE block (health technologies) | 12/2024 | ||
| Reconstruction of the interior of the monoblock AE | 5/2026 | ||
| OP for designer and subsequent execution of project documentation | 12/2024 | ||
| Public procurement of the work contractor | 5/2025 | ||
| Implementation | 5/2026 | ||
| Reconstruction of obstetrics department | 1/2026 | ||
| Public procurement of the work contractor | 12/2024 | ||
| Implementation | 1/2026 | ||
| Improving the energy efficiency of the AE monoblock
(Reduction of the energy intensity of NsP Prievidza based in Bojnice (Pavilion E) |
1/2026 | ||
| Public procurement | 12/2024 | ||
| Implementation | 1/2026 |