| The beneficiary shall: | Poprad Hospital, a.s. |
| Project name: | Hospital Poprad, a.s |
![]()
| ACTIVITIES | Expected date of completion |
Real date of completion |
|
| Project preparation | 02/2023 | 02/2023 | |
| Construction procedure | 07/2023 | 11/2023 | |
| Building permit | 08/2023 | 11/2023 | |
| Procurement for the contractor | 06/2023 | 06/2023 | |
| Termination of public works contracts for the contractor | 12/2023 | 03/2024 | |
| Contract concluded with construction contractor | 12/2023 | 03/2024 | |
| Start of construction - 1st stage | 02/2024 | ||
| End of construction - 1st stage | 05/2024 | ||
| Start of construction - 2nd stage | 06/204 | ||
| End of construction - 2nd stage | 06/206 | ||
| Collusion | 06/206 |