| The beneficiary shall: | National Institute of Heart and Vascular Diseases, a.s. |
| Project name: | Strengthening berth and operating capacity National Institute of Heart and Vascular Diseases, a.s. |
![]()
| ACTIVITIES | Expected date of completion |
Real date of completion |
|
| Pre-project preparation | 09/2023 | 09/2023 | |
| Project preparation | 12/2023 | 01.2024 | |
| Procedure for declaring building modifications | 03/2024 | 03/2024 | |
| Procurement for the contractor | 12/2023 | 01.2024 | |
| Termination of public works contracts for the contractor | 03/2024 | ||
| Contract concluded with construction contractor | 03/2024 | ||
| Start of construction | 04/2024 | ||
| End of construction | 06/206 | ||
| Start of operation | 12/2026 |